Project: |
SunTrust |
Building
Type: |
Check Clearing Operations Center |
| Location: |
Morrow, Georgia |
General
Contractor: |
Beers Construction |
| Wall Design: |
6" Tilt-up Wall Panels |
| Details: |
200,000 sf slab
43,000 sf Tilt-up Panels
Fast track design with load bearing Tilt-up standing in under 6 weeks, despite construction record cold & rain in the middle of the Christmas/New Years holidays.
Polar-set Antifreeze additive added to almost every pour because of freezing conditions.
|
 |
Project: |
Private Storage |
Building
Type: |
Three-Story Public Storage Building |
| Location: |
Decatur, Georgia |
General
Contractor: |
Dooley & Mack Constructors, Inc. |
| Wall Design: |
N/A |
| Details: |
110,000 sf multi-story
75,000 sf concrete paving
Formed and poured two elevator shafts
Worked with contractor to overcome difficult site conditions.
|
 |
Project: |
Komatsu |
Building
Type: |
Showroom/Training Facility |
| Location: |
Cartersville, Georgia |
General
Contractor: |
Kajima |
| Wall Design: |
N/A |
| Details: |
6 Tilt-up/Brick on Framing/Metal Building
Details: &Mac183; 42,000 s.f. multi-use slab
21,400 s.f. Meta building shop slab
17,100 s.f. truck apron
Forklift drive and ramp
Poured in place retaining & foundation walls, sidewalk & cast in place stairs
Jib crane & equipment foundations
|
Contact us for additional information on some of our other commercial projects.
|